The National Land Commission (NLC) has disclosed that it has facilitated compensation awards worth approximately KSh1.3 billion for landowners affected by the construction of the multibillion-shilling Isiolo-Mandera Highway.
In a statement issued on Wednesday, November 18, the commission clarified its role in the compensation process following concerns raised by the World Bank over delays in paying residents whose properties are affected by the project.
NLC maintained that its responsibility is limited to conducting land valuations, verifying assets and preparing compensation schedules, while the Kenya National Highways Authority (KeNHA) handles the processing and disbursement of payments in line with World Bank directives.
The clarification came after the World Bank warned that delays in compensating affected residents were disrupting construction activities and exposing the project to additional costs estimated at KSh1.2 billion every month.
According to NLC, compensation payments for the Isiolo-Kulamawe-Modogashe section are ongoing, with KeNHA awaiting approval from the World Bank to release KSh554.9 million to approximately 1,280 project-affected persons.
For the Wajir-Kotulo section, the commission said it had approved compensation awards amounting to KSh824 million for 1,619 affected individuals, with the schedules forwarded to KeNHA to facilitate payment.
NLC also revealed that KSh497 million had been approved for 296 affected persons along the Isiolo-Kachuru section.
Meanwhile, the commission reported progress in the Dimu-Elwak section, where asset verification involving more than 1,105 affected persons had been conducted. The valuation exercise was expected to be completed by the end of November 2026.
Despite the progress, NLC identified several challenges affecting the compensation exercise, including ongoing court cases, insecurity along parts of the highway, uncollected compensation offers and difficulties tracing some affected landowners.
The commission also cited unresolved succession matters involving deceased property owners and disputes surrounding land acquisition as additional obstacles.
The developments follow a warning from the World Bank, which indicated that delays in securing unrestricted access to construction sites were increasing project expenses and threatening the implementation schedule.
The 740-kilometre Isiolo-Mandera Highway is being implemented under the Horn of Africa Gateway Development Project and is expected to improve connectivity between northern Kenya and neighbouring countries.
As of October 26, 2026, construction had reportedly reached 60 per cent completion. The project was initially expected to be completed by January 2028, but the timeline has since been pushed to approximately 2030.
NLC has pledged to continue working with KeNHA, the World Bank and other relevant agencies to address outstanding compensation issues and protect the rights of residents affected by the road construction.